In England, most homeowners can fit solar panels to their roof without planning permission. They're allowed as "permitted development", as long as you stay within some simple limits. The rules were updated on 27 August 2026 to cover walls, balconies and plug-in panels too.
This guide covers England. Wales and Scotland have their own rules.
The limits for a house
You don't need planning permission for solar panels on a house, or on a building in its garden such as a garage, if:
- Sloping roof: the panels stick out no more than 0.2 metres from the roof surface, and no part is higher than the highest part of the roof (chimneys don't count).
- Flat roof: no part of the panels is more than 0.6 metres above the highest part of the roof.
- Wall: the panels stick out no more than 0.2 metres if the wall is next to a road, or 0.4 metres otherwise. The same limits apply to balconies and roof railings.
Panels must also be placed, as far as practicable, to minimise their effect on how the building looks and on the area, and removed when no longer needed.
When you do need permission
- Listed buildings: permitted development doesn't apply. You'll need planning permission and usually listed building consent.
- Scheduled monuments: not permitted.
- Conservation areas and World Heritage Sites: you can't fit panels on a wall, balcony or roof railing that faces a road without permission. Panels on the roof, including the front slope, are generally still allowed.
- Flat roofs in protected areas: in conservation areas, national parks and National Landscapes (formerly AONBs), you must ask the council first whether it needs to approve how the panels look.
- Article 4 directions: some councils have removed permitted development rights in particular streets or conservation areas. If your home is covered, you'll need permission even for work that's normally allowed.
Local rules on the south coast
Article 4 directions vary street by street. Some examples from the areas we cover:
- Chichester city centre: panels on any roof slope facing a road, open space or waterway need permission. See solar panels in Chichester.
- Langstone, Havant: panels on any part of a house facing the road need permission. See solar panels in Havant and Emsworth.
- Southampton: the council says panels may need permission in seven conservation areas, mostly in SO17, including Portswood Residents Gardens and Uplands Estate. See solar panels in Southampton.
- Isle of Wight: several conservation areas have local rules. In Seaview, for example, changes to a roof facing a road, the sea or open space need permission. See solar panels on the Isle of Wight.
If you live in a conservation area, check the council's conservation area page or ask its planning team before you sign a contract.
National parks
Roof panels on houses are mostly still permitted development inside national parks, with the extra flat-roof check above. The parks also publish design advice:
- South Downs: the National Park Authority's renewable energy guidance supports well-designed small-scale solar, and suggests solar tiles for prominent roofs in conservation areas. See Petersfield.
- New Forest: the design guide asks for non-reflective panels fitted as flush as possible, not above the roofline and not on dormers. See the New Forest.
Flats and leasehold homes
Since December 2023 the rules also cover blocks of flats, with similar limits. But permitted development is about planning, not ownership. If you own a flat, the roof usually belongs to the freeholder, so you'll need their agreement under your lease before anything is fitted. Tenants need their landlord's permission.
Plug-in solar
Small plug-in panels (up to 800 W) are covered by the same rules, but can't be fixed to a wooden wall, balcony or timber-clad wall. See plug-in solar panels.
Other things to sort out
Planning is only one part. Your installer should also:
- make sure the work meets Building Regulations, for example that the roof can take the weight;
- notify your electricity network operator about the system; and
- register it with MCS, which you'll need for Smart Export Guarantee payments.
Ready to see what panels could save you? Try our calculator.
Frequently asked questions
Do I need planning permission for solar panels on my house?
Usually not, in England. Roof panels on a house are 'permitted development' as long as they stick out no more than 0.2 metres from a sloping roof and don't go higher than the highest part of the roof (chimneys aside). Listed buildings, some conservation areas and a few other cases are different.
Can I put solar panels on the front of my house?
On the roof, yes, in most places, including the front slope. Wall-mounted panels on a wall facing the road aren't allowed without permission in a conservation area. Some councils also have local rules (Article 4 directions) that remove the right to fit panels on roofs facing the road, so check if you live in a conservation area.
Can I have solar panels in a conservation area?
Generally yes, on the roof, without planning permission. You can't fit them on a wall, balcony or roof railing facing the road, and flat-roof panels need the council's approval of how they look first. A few areas have extra local rules, such as central Chichester and Langstone near Havant.
Do I need permission for solar panels on a listed building?
Yes. Permitted development doesn't apply to listed buildings, so you'll need planning permission and usually listed building consent. Speak to your council's conservation officer early.
Do I need planning permission for solar panels on a flat roof?
Not usually. Since December 2023, panels on a flat roof are permitted development if they're no more than 0.6 metres above the highest part of the roof. In conservation areas, national parks and National Landscapes, you must first ask the council whether it needs to approve how they look.
Do the same rules apply in Wales and Scotland?
No. This guide covers England. Wales and Scotland have their own permitted development rules for solar, so check with your council there.
Sources
- The Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2, Part 14, Class A (as amended): https://www.legislation.gov.uk/uksi/2015/596/schedule/2/part/14/crossheading/class-a-installation-or-alteration-etc-of-solar-equipment-on-domestic-premises
- The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (SI 2026/896), in force 27 August 2026: https://www.legislation.gov.uk/uksi/2026/896/made
- SI 2023/1279 (flat roofs and blocks of flats, from 21 December 2023): https://www.legislation.gov.uk/uksi/2023/1279/article/4/made
- Planning Portal, changes to permitted development rules for domestic solar (28 August 2026): https://blog.planningportal.co.uk/2026/08/28/changes-to-permitted-development-rules-for-domestic-solar-installations/
- South Downs National Park Authority, Small Scale Renewable Energy Technical Advice Note: https://www.southdowns.gov.uk/planning-policy/supplementary-planning-documents/technical-advice-notes-tans/small-scale-renewable-energy-technical-advice-note-tan/
- New Forest National Park Authority, Design Guide SPD: https://www.newforestnpa.gov.uk/wp-content/uploads/2026/01/New-Forest-National-Park-Design-Guide-SPD.pdf